Download Method Statement Switchgears PDF

TitleMethod Statement Switchgears
TagsTechnology Occupational Safety And Health Crane (Machine) Personal Protective Equipment
File Size120.5 KB
Total Pages6
Table of Contents
                            1. Purpose
2. Scope
3. Definitions
4. References
5. Responsibilities
	5.1. Site Manager:
	5.2. Site Engineer:
	5.3. HSE Manager from PPR:
	5.4. Supervising Engineer:
6. IMPLEMENTATION
	6.1. General
	6.2. Transport
	6.3. Preparing Element Prior to Installation
	6.4. Installation
7. HSE
	7.1. Personal protective equipment
	7.2. Machinery
	7.3. Lifting operations
	7.4. Access and housekeeping
	7.5. Manual handling
	7.6. Fire prevention and protection
	7.7. Emergency response
                        
Document Text Contents
Page 4

KESİR MÜHENDİSLİK ELEKTRİK LTD ŞTİ.

METHOD STATEMENT OF SWITCHGEARS
INSTALLATION

Dok. No. TL 751.04
Yay.
Tarihi

18.07.201
1

Rev. No. 00
Rev.
Tarihi

--

Sayfa
No:

4/6

6.2. Transport
Transportation of Switchgears is placed properly. Crane will be used and all necessary precaution
matures will be taken. Provide truck to transportation of Switchgears and accessories from
storage area to the field. Use crane for lifting and carrying Switchgears. When Crane will be used
according to 7.3. lifting operation. It will be stayed suitable places, so it prevents to work and
workers work safely.

6.3. Preparing Element Prior to Installation
Check last revision of approved project then start installation. Request form for materials will be
prepared. Projects will be inspected and it will be selected where personnel will start installation
of Switchgears. After it reaches the site, it will be unpacked according to instruction about
switchgears.

6.4. Installation
Installation will be carried out in accordance with the last approved revision of the installation
projects. Switchgears will be transported from storage to site with crane and pickup. While it will
be carried, it will be fixed safely in the truck board. The assembly drawings will be checked on
the place of installation. At the working area, the panels will be placed in a way that will not
prevent safe access and egress. According to projects layout, it will be taken in area. Personnel
will use transpallet and rods for alignment of panels. Rods will be helped alignment of panels.
Panels will be placed from crane to transpallet. Then it will be unpacked according to instruction
on switchgears. Panels will be leveled with help of rods. Inside the room winch, which is a
manual device that is used to pull panel, will be used properly. Operator’ documents will be
prepared by us and training will be given by HSE. All documents will be checked. Crane will be
set safe area. Crane will be used by competent person. Panels will be lifted according to 7.3.
lifting operation. Installation of panels will be executed according to the requirements. Panel will
be erected others with bolts, so alignment will be made properly. Then all panels will be erected
on the floor, when the panels will be sure same level. PPE will be used all level of action. When
all of works will be done, it will be controlled all equipment and bolts that is ready to use. After
the works is done daily, working areas will be cleaned.

7. HSE

7.1. Personal protective equipment
PPE will be provided and used in accordance with requirements. Helmet, safety glasses, high
visibility vest, and safety shoes will be used at all the times.
When work in dusty environment personnel will use dust protective half masks.
Hearing protection will be used where exposure levels exceed 85 dB.
When work at height fall arrest system will be used if other protective measures are not feasible.


KKS No. 440-00-YF-SNO-KSR-002
Page 4 of 6

Page 5

KESİR MÜHENDİSLİK ELEKTRİK LTD ŞTİ.

METHOD STATEMENT OF SWITCHGEARS
INSTALLATION

Dok. No. TL 751.04
Yay.
Tarihi

18.07.201
1

Rev. No. 00
Rev.
Tarihi

--

Sayfa
No:

5/6

7.2. Machinery
All machinery, equipment and tools will be maintained in good working order; will be inspected
regularly; and will be operated by competent persons. All necessary measures will be in place in
order to prevent environmental pollution. In case of oil spill an immediate actions will be taken
to localize and clean the area in accordance with the procedure. Guards will be in place to protect
workers from moving parts. Electrical tools will be double insulated and grounded connected to
ground fault circuit interrupters (GFCI).
All vehicles will have backing warning device. Banks man will guide vehicles
in narrow work places and when reversing. Vehicles will not pass, will not be
positioned or parked close to excavation edges.

7.3. Lifting operations
Execution of the lifting operations will comply with the provisions of the
requirements.
Cranes will be set on even flat ground. Pads will be used under the outriggers
feet where necessary.
When work is close to excavation the lifting equipment will be positioned at
least 1 meter away from the excavation edge in order to prevent earth
collapse. Working limits of the lifting equipment stipulated by the
manufacturer will not be exceeded. Safe clearance will be kept from
overhead power lines.

Lifting of the stacks of panels will be carried out only with fabric slings with the proper safe
working load limit. The slings will be inspected and color-coded.

Lifting operation shall be segregated from other persons on site. All personnel and third
parties will be kept out of any area where they might be struck or crushed by
a load or lifting equipment if it swings, shifts or falls.

Operators of lifting equipment will be able to see the full path of the load or have a signaler with
an appropriate means of communication to guide them. Operator will obey an
emergency stop signal at all times, no matter who gives it. The operator will
not leave the operating controls while the load is suspended.
Taglines will be used where it is necessary load to be guided and controlled.
Taglines of nonconductive material will be used when lifting operation is
close to overhead power lines.

Lifting equipment will not be used in the open air where weather conditions could affect the
integrity of the equipment or expose persons to danger.

KKS No. 440-00-YF-SNO-KSR-002
Page 5 of 6